Construction of Buyende Town Water Supply System.
Abstract
This project report contains details for the construction of the Buyende Town Water Supply
System project, Procurement Reference Number MWE/WSDF-E/WRKS/14-15/00118 from
start to practical completion, in which the author was involved as a Contractor’s Site Agent.
The project was designed to cater for the need of water supply in Buyende district and its
original contract value was UGX. 2,444,757,819. The project commenced on 21st September
2016 and was envisaged to be completed within 12 months. However, practical completion
was achieved on 20th February 2018, having expended 42% (5 months) more time than it was
planned.
The report details the construction methodology and project management practices exercised
by the author during execution of the project. It contains the major activities and methodology
adopted on the project right from the bidding and award of the contract, to the end of the
Defects Liability Period (DLP), and it expressly details construction works and contract
administration procedures undertaken during project execution including aspects of safety and
health.
The different challenges encountered on the project and how they were solved, plus the lessons
learned from the project execution in as far as construction project management is concerned
are also detailed. The report also details the conclusions drawn by the author and the
recommendations made in light of successful management of similar projects going forward.
Collections
Related items
Showing items related by title, author, creator and subject.
-
Effect of upper catchment management and water cover plants on quantity and quality of water in reservoirs and their implications on Livestock Water Productivity (LWP)
Zziwa, Emmanuel (2009-01)Seasonal water fluctuations both in quality and quantity negatively affect livestock production and subsequently reduce livestock-water productivity (LWP) in rainfed pastoral production systems. The major contributing ... -
A study of the impact of water supply network expansions on water network hydraulics: a case study of zone 8, Kampala Water
Nyende, Stephen (Makerere University, 2006-08)The National Water and Sewerage Corporation (NWSC) in a drive to provide wide water supply coverage and to maximise profits has increased the number of customer connections through a massive network expansion. At the same ... -
Modelling of land use and land cover to predict future water demand and inform infrastructural planning in the Kampala Water Service Area of National Water and Sewerage Corporation
Namawejje, Doreen (Makerere University, 2022-01-28)Land cover is a fundamental variable that impacts many parts of the global environment. Changes in land cover can have far-reaching consequences at local and global levels, therefore monitoring the changes of land use and ...