Rehabilitation and Upgrading of Mulago Hospital into a Super Specialized National Referral Hospital.
Abstract
The lack of construction management professionals has been at the bottom of several unbecoming practices and occurrences in the construction industry such as: collapse of buildings, incomplete projects, cost escalations, poor construction process administration, lack of technical planning, poor construction controls, unethical procurement procedures, lack of proper supervision, poor production of work, lack of site progress reports, inadequate specifications, low quality work, and lack of technical information during the construction process. All these have had a devastating effect on the national economy and as well as the social fabric
This report gives a brief summary of the construction project management practices which include Planning, scoping, Time, Cost, Quality (Aftab Hameed Memon1, 2011) (Chan & and Kumaraswamy, 1997) (Frimpong, Oluwoy, & Crawford, 2003) (Kaliba, Muya, & Mumba, 2009) (Kaming, Olomolaiye, Holt, & Harris, 1997) (Mansfield, Ugwu, & Doran, 1994) (D. & and Hall, 1995) (Sweis, Sweis, Abu Hammad, & Shbpul, 2008) (Yang & Ou, 2008) (Assaf S.A Al-Hejji S, 2006)and Procurement on our construction sites today with case in point, the Rehabilitation and Upgrading of Mulago hospital into a Super Specialised National Referral Hospital.
The report brings out the practical experience of the Author on this project and it looks at the parties to contract, key stake holders, time and cost challenges, variations, project payment and cost control as encountered of Mulago Project.
The report also provides project management challenges and possible recommendations to areas of improvement so as to uplift construction project management to another level.
Collections
Related items
Showing items related by title, author, creator and subject.
-
Assessing the effectiveness of healthcare waste management in Uganda’s Public Hospitals: a case study of China-Uganda Friendship Hospital-Naguru and Kiruddu Hospital
Tusubira, Samuel (Makerere University, 2023-01)This study is to assess the effectiveness of Healthcare waste management in Uganda public hospitals; a case study of China-Uganda Friendship Hospital-Naguru and Kiruddu Hospital. The study was guided by study objectives ... -
Navigating project management challenges in modern hospital construction during the construction phase: “a case study of the proposed hospital expansion works on plot 14B Akii- Bua Road, Nakasero for Nakasero Hospital Ltd”
Tebandeke, Frank (Makerere University, 2024-07)In this technical report, the author presents an analysis of the project management challenges encountered in modern hospital construction during the construction phase, a case study of Nakasero Hospital Expansion Project ... -
What could be achieved with greater public hospital autonomy? Comparison of public and PNFP hospitals in Uganda.
Seangooba, Freddie; Atuyambe, Lynn; McPake, Barbara; Hanson, Kara; Okuonzi, Sam (Wiley InterScience, 2002)The policy of hospital autonomy has been discussed for some time in Uganda. There is little evidence from Uganda or elsewhere that increased autonomy will improve hospital performance. This article compares the performance ...